A can do a piece of work in 10 days B can do it in 15 days.They work together for 5 days and rest of work done by C in 2 days.If they get 4800 rs for whole work, how should they devide the money? How can solve this???
Days needed by C to do 1 Work not given. So we can't approach the problem by LCM method. I think this is the solution. If wrong please correct me.
2400 rs for A 1600 rs for B 800 rs for C This is correct answer. This is done by general method but can't by LCM method.